Easement Work

IARWC is finalizing the remaining easement documents and a representative from MHE (engineering group) will be contacting those property owners to discuss the procurement of the water line routing.

IARWC timeline for the intial project is as follows:

2023 – 2026 Finalize engineering

2023 – 2026 Easement Procurement for Phases 1A, 1B, 2, & 3

2025 Bid project - Phase 1A 

2026 Loan closing with Rural Development Phase 1A

2026 Construction - Phase 1A Begins 18 to 24 months to complete

2026/2027 Bid project - Phase 1B, 2 & 3

2027 Construction - Phase 1B, 2 & 3 begins 9 to 12 months to complete

2028 – 2029 Finish up/clean-up